All streets have been milled and the binder course has been installed. The tentative schedule is as follows:
1. Dallett – Wearing course is installed.
2. South Passage – Wearing course to be installed today.
3. Hennig – Wearing course to be installed today.
4. Woody Crest – Additional concrete curb to be installed. Thursday/Friday, wearing course to be installed early next week.
5. Grove Road – Wearing course to be installed early next week.